LAKEWOOD

Harvesters will continue to work north up the west side of the lake towards Ashville Bay. Once completed they will go to the northernest point of their route on east side of the lake and begin working south (Bellview Road).

Shore crews will continue working south through Burtis Bay to Celoron Park. Once completed they will travel to the northernest point of their route on east side of the lake and begin working south following the harvesting crew.

LONG POINT

Harvesters will continue south along east side of lake to Colburns/Phillip Mills area. Once complete they will travel across the lake to Ashville Bay and begin working north along the west side of the lake to the bridge.

Shore crews will continue working south through Oriental Park. Once that is complete, they will begin Lakeside Drive. 

MAYVILLE

We will be moving equipment north to Mayville on Thursday afternoon. We will need (1) harvester, (1) transport, (1) barge crew to make the move. The other equipment will move up as needed. We had planned to begin working in the north this week however after surveying the area we found the need to be much greater below Long Point at this time. 

MOBI-TRACK  

We will be partnering with the Town of Chautauqua offering support to their mobi-trac program beginning Monday, June 29, 2020. This week those crews will be working in Bemus Bay. This partnership will help the program be much more efficient and effective.