Regular Season Week #4 Work Plan
This week will mark the first completed route for all harvester crews as well as the start of the Mobi-Trac program which should speed up the routes for our shore crews.
The north lake harvesters will continue to work their way through Hartfield Bay to the Lutheran Camp. Then from Mayville Park to Prendergast Point. Shore crew will continue along the east shore from Hartfield to the Mayville Park then begin the west shore.
The south lake harvesters will continue along their route to the Celoron marinas and then into Burtis Bay and back up the west shore. Lakewood shore crews will continue working north along the west shore to Ashville Bay then cross to the Cheney Farm and begin working south towards Greenhurst.
The mid-lake harvesters will begin working the east shore from the Lutheran Camp heading south to Long Point. Once complete they will continue along the east shore to the Cheney Farm. The shore crew will continue south along the east shore to the bridge. Once complete they will begin working along the west shore from Upper Stow to Prendergast Point.

Their will be two Mobi-Trac crews this year; one north, one south. The north crew will begin working south along the east shore from Mayville Park to the Bridge. The south crew will begin at the bridge working south along the east shore to Old Fluvanna. Once the east shores are complete, we will be moving to the west. The first pass is always the slowest. We will be getting as far as we can each day depending on what we find and the weather.
Have a great week!