This week the South Harvester Crew will be finishing up along Old Fluvanna then crossing to Ashville Bay and working north along the west shore to Cheney’s Point. Once that area is completed they will cross to the east shore working south from the Cheney Farm to Sheldon Hall. The Shore Crew will continue along the west shore of Sherman’s Bay to Ashville Bay Marina. Once complete they will be crossing to the Cheney Farm working south towards Greenhurst.
The South Mobi Crew will continue south along the east shore from Greenhurst to Denslow at the end of Old Fluvanna. Then they will cross to the Celoron Marinas, working north along the west shore. They will continue north along the west shore through Burtis Bay and into Lakewood.
The Center Harvesting Crew will continue through Whitney Bay working north to Chautauqua Institution. Once complete they will cross to the east shore working south from the Lutheran Camp towards Long Point, then continuing south to the Cheney Farm. The Shore Crew will be working south along the east shore from Midway Park through Maple Springs back to Long Point. Then they will continue south along the east shore through Bemus to the Cheney Farm.

The North Harvesting and Shore Crew will continue south along the west shore from Irwin Bay to Chautauqua Institution. Once complete they will work south along the east shore from Mayville Park through Hartfield Bay and Dewittville Bay to the Lutheran Camp.
The North Mobi Crew will continue south along the east shore from Dewittville Bay to the Bemus/Stow Ferry, then cross and begin working north along the west shore.
PLEASE NOTE: Our harvesting crews will NOT be working in any of the areas treated with ProcellaCOR in June. We have been asked by the applicators not to harvest in these areas for the next 30 days. Please understand, there are widespread treatment areas throughout the lake. To learn more about what areas are being treated please contact your town or village.